The 12-stage export process timeline

1

Day 0

PI Signed + Advance Received

Proforma invoice signed by both sides. Advance (30% domestic / 50% international first-order) received via NEFT or wire. We confirm receipt via email + WhatsApp.

PRE-PRODUCTION

2

Day 1

Production Lot Reserved

Lot scheduled in our 6-month rolling production planner. Spec sheet locked (including any buyer-custom parameters). Raw material upstream allocated to your lot.

PRE-PRODUCTION

3

Day 2-5

Production + In-Process QC

Distillation / fractionation / cold-pressing per the SKU SOP. In-process QC parameters monitored — vapour temperature, column pressure, reflux ratio. In-process samples drawn at critical points to verify chemistry.

PRODUCTION

4

Day 5-6

Finished-Product Testing (In-House)

In-house QC lab tests the full lot — specific gravity, refractive index, optical rotation, GC assay, GC-MS chromatogram with peak ID, organoleptic verification. In-house COA generated.

QC

5

Day 6-8

NABL Third-Party QC Verification

Representative sample sent to NABL-accredited lab. Heavy-metals + residual-solvent + microbial panel as applicable. Third-party COA returned. 36-month retain sample preserved.

QC

6

Day 8-9

Packaging + Master Label Application

Lot packed per spec (25 kg HDPE drum, 180 kg MS drum, IBC, or FCL configuration). Master label applied: SKU, botanical/INCI, lot number, manufacture date, retest date, QR code → digital COA.

PACKAGING

7

Day 9

Export Paperwork Pack Assembled

Commercial invoice + packing list + COA + GC-MS chromatogram + NABL third-party COA + MSDS + IFRA (if fragrance) + Allergen-23 + pharmacopoeia compliance (if pharma) + country-of-origin + Apostille (if LATAM/GCC).

PAPERWORK

8

Day 10

Truck Dispatch to Port

Truck dispatched from Bulandshahar Road plant via NH corridor to JNPT / Mundra / Hazira / Chennai. WhatsApp ping with truck driver number + GPS tracking link.

EXPORT

9

Day 11-13

Port Clearance + Container Loading

Export customs clearance with our export-customs agent. Container assigned + loaded. B/L issued by shipping line. Original B/L scanned + emailed; couriered as required for buyer’s LC documentation.

EXPORT

10

Day 14+

Sea Freight Transit

Container loaded onto vessel for buyer’s destination port. Transit time: 9 days (GCC) → 32 days (LATAM). Buyer can track via shipping line website using B/L number.

TRANSIT

11

Day arrival

Destination Port + Buyer Customs

Container arrives at buyer’s destination port. Buyer’s freight forwarder handles destination customs clearance using the paperwork pack we shipped. Typical 2–7 days at destination.

DELIVERY

12

Day final

Delivery to Buyer Warehouse

Container cleared and delivered to buyer’s warehouse. Buyer’s QA team verifies COA + paperwork pack matches the consignment. Retain-sample reference filed in batch record.

DELIVERY

Process variations by buyer type

India domestic

Stages 1–8 same. Skip stages 9, 11. Stage 10 = truck dispatch direct to buyer warehouse (1–7 days transit depending on city).

FOB international

Full 12 stages. Buyer’s freight forwarder takes over at port-of-loading (after stage 11).

CIF international

Full 12 stages. We continue to handle freight + insurance through stage 12 destination port. Buyer handles destination customs.

DAP international

Full 12 stages. We handle everything except destination duties + taxes. Buyer just opens the warehouse door.

EXW

Stages 1–9 same. Stage 10 = buyer’s forwarder picks up at our plant gate. Buyer handles everything onwards.

Air freight (samples)

Compressed to stages 1–8 (production + QC same), then stage 9 = air-freight via DEL airport. 5–10 day total port-to-buyer.

Where buyers typically see lead-time variance

  • Stage 1 (PI advance): 0–3 days depending on buyer-side banking speed
  • Stage 2-5 (production): 0 days if reservation slot pre-locked; 2–5 days if scheduling fresh
  • Stage 11 (port clearance): 1–4 days depending on JNPT/Mundra/Hazira port congestion
  • Stage 12 (destination customs): 2–10 days; varies widely by country
  • Stage 14+ (sea transit): 9–32 days depending on origin-destination route

Want a firm timeline commitment with your quote? Send the RFQ.

Quote PDF includes specific lead-time per route + Incoterm + freight mode + capacity reservation status.